Decision details

Appointment of services for Guildford Park Road – Project Management and Full Design Team

Decision Maker: Joint Strategic Director - Place

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Contract Award

Contract Value: £924,455.00

Successful Company: AECOM

Contract Start: September 2021

Contract End: Completion of Services

A review of the CCS RM3741 Project Management and Full Design Team Services framework revealed that AECOM were offering the best rate and offered a Direct Award route based on the circumstances of the project requirements.

Reasons for the decision:

The project has been on hold for many months whilst a new Mandate and Business Case was developed. These are now in place and Officers have approval to develop a new planning application. Given the delays to the project, there is a desire to do this as expediently as possible.
The Council will require multi-disciplinary professional services to develop the new application,
AECOM are able to provide the necessary services at a rate which has been deemed competitive.


Alternative options considered:

SCAPE (Perfect Circle) framework was assessed and did not evidence best value for this appointment.

Publication date: 04/10/2021

Date of decision: 04/10/2021

Effective from: 12/10/2021