(1)  That the sum of £3.93 million required for the Hotspots project (ref. P16(p)), that is currently on the provisional capital programme, be moved to the approved capital programme. 

 

(2)  That the sum of £1.033 million required for the Town Centre Approaches project (ref. P14(p)), that is currently on the provisional capital programme, be moved to the approved capital programme. 

 

Decision type: Key

Reason Key: Significantly affects 2 or more wards within the Borough;

Decision status: Recommendations Approved

Wards affected: (All Wards);

Notice of proposed decision first published: 28/08/2018

Decision due: 30 Oct 2018 by Executive

Lead member: Lead Councillor for Strategy and Corporate Services, Lead Councillor for Strategy and Corporate Services

Lead director: Joint Strategic Director - Place, Joint Strategic Director - Place

Contact: Rob Curtis Email: rob.curtis@guildford.gov.uk, Rob Curtis Email: rob.curtis@guildford.gov.uk.