Issue - decisions

Town Centre Public Realm Improvements

23/04/2019 - Guildford Public Realm Improvement Project

Decision:

(1)     That the proposed Town Centre Public Realm Improvements, as described in the report submitted to the Executive, be approved.

 

(2)     That the sum of £965,000 retained for public realm improvements and £260,000 set aside for the installation of the High Street safety barrier measures be transferred from the provisional to the approved capital programme to deliver the scheme, and that any external contributions, including the £10,000 from the BID Board, be allocated to the approved capital programme towards this scheme.

 

(3)     That the Director of Environment be authorised, in consultation with the relevant Lead Councillor, to progress the scheme to completion and seek relevant statutory consents as required.

 

Reason for Recommendation:

To progress phase 2 of the Town Centre Public Realm Improvements.

 

Alternative options considered and rejected by the Executive:

None

 

Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted:

None