Agenda item

Ash Road Bridge Scheme Update and Budget Approval

Minutes:

A recorded vote was requested in respect of the motion to approve the budget and funding strategy for the Ash Road Bridge project, which was supported by four other councillors in accordance with Council Procedure Rule 19 (d).

 

The Council considered an update report on progress with the Ash Road Bridge Scheme, which included a reappraisal of the budget and funding in respect of the project.  Councillors noted that the project comprised a long-term infrastructure solution to the current and future issues posed by the Ash level crossing, including increased usage associated with housing growth in the Ash and Tongham area and greater barrier downtime resulting from enhanced rail use of the North Downs Line.

 

The Scheme was being delivered in two Stages. Stage 1 was the delivery of the road bridge over the railway line (and closure of the level crossing to motorised vehicles), and Stage 2 the delivery of the footbridge in the vicinity of Ash level crossing, to enable Ash level crossing to be closed permanently to all users.

 

The Council had approved the Scheme in April 2021, with a budget of £33.8 million for Stage 1 (road bridge) and £5.02 million for Stage 2 (footbridge) and funding from Homes England of £23.9 million.  Due to challenging economic and market conditions the budget for Stage 1 (road bridge) had increased. Although, the Ash Road Bridge would bring substantial improvements to the local community and economy, the Executive was concerned about how the ongoing annual costs would be met. In noting the progress of this project since it was initially commissioned in 2015 and the benefits it would bring, the Executive had requested that further discussions be held with Surrey County Council as the transport and highways authority, Network Rail and Homes England on the ongoing impact of the costs of the bridge to local public services.

 

The report had set out, in the exempt appendices, the new budget and funding strategy for Stage 1 (road bridge) of the Scheme. The report noted that the final details of this could be subject to change following ongoing evaluation of the tenders received from the contractors in late January 2023 and their final offer in March 2023, including the impact on the Medium-Term Financial Plan.  The report had also set out the funding strategy for Stage 2 of the Scheme (the footbridge).

 

The Council was informed that the approved budget for the Scheme was £38.91 million, being £33.89 million for the road bridge (Stage 1) and £5.02 million for the footbridge (Stage 2) (excluding borrowing costs.) The road bridge budget was slightly higher than that which had been approved by the Council in April 2021 (£38.79million) as the budget had subsequently combined with a separate approved budget for land acquisition costs for the Ash Road Bridge Scheme equivalent to £0.12 million. The revised budget was £44.5 million, being £44.0 million for the road bridge and £0.5 million for the footbridge (excluding borrowing costs.) The increase to the budget was therefore £5.59 million.

 

The Order Paper circulated to councillors at the meeting included a further update to the Funding Paper (Exempt Appendix 3 to the Council report) which had set out the implications for the funding strategy of the recent offer by Surrey County Council to make a contribution of £5m towards the scheme.

 

At its meeting earlier in the day, the Executive had also considered the report, including the further update to the Funding Paper, and had recommended to the Council approval of the budget and funding strategy, as updated.

 

The Lead Councillor for Regeneration, Councillor John Rigg, proposed and the Leader of the Council, Councillor Julia McShane, seconded a motion to approve the budget and funding strategy as set out in the Exempt Appendices 2 and 3 to the report submitted to the Council, subject to the revisions to the Funding Paper in Appendix 3, as set out in the Order Paper.

 

The Council debated the information contained in the public report.  The following points were made by councillors:

 

·       The Lead Councillor noted that, in addition to Surrey County Council’s contribution, it was possible that further grants might become available next year, but no allowance had been made in the budget and discussions were being held with Network Rail in respect of a contribution to the footbridge.

·       The project was hugely important in terms of infrastructure delivery, and it was long overdue

·       The bridge would create traffic problems and make rat-running worse

·       There was a need to work with the County Council to mitigate against some of the highways issues identified

·       Network Rail had previously classified the safety risk as medium-to-high for pedestrians, not for vehicles on this crossing.  A footbridge would nullify this risk.

·       Concern over the lack of clarity over the final cost of the bridge and the contingency being factored in being too low.

·       All the highways and traffic related issues were debated at length and taken into account both as part of the Local Plan, when it was a requirement of Policy A31 and when planning permission was granted in 2021.

·       The rat running through local roadswas mainly caused by people who want to avoid the delays at the level crossing.

·       Whilst it was true that much of the new housing would not directly link to the bridge, people from those properties would be feeding onto the same roads that were already being used to avoid the crossing.

·       In response to claims that some local people did not want the road bridge, the Council’s attention was drawn to a petition lodged in 2004 to the former Guildford Local Committee from Ash residents asking for a bridge to be built on the basis that it would remove a congestion hotspot delaying vehicles, pedestrians and cyclists caused by the present level crossing.

·       Construction of the significant additional housing in the area was not conditional on the construction of the road bridge.

·       Failure to deliver a road bridge now, and take advantage of significant government funding, might mean that a bridge would never be built.  

·       Surrey County Council, as the Highway Authority, should be paying for and building this bridge.

·       Delays in getting to this stage had caused the significant increase in cost from £12.9m to £44m.

·       The benefits of the bridge had not been set out, neither had the mitigations or the cost of them.  There also appeared to be little evidence of public approval for the bridge.

·       In response to concerns that further delays and the already tight timescale might prevent the Council from drawing down the Homes England funding, the Lead Councillor reassured the Council that Homes England had indicated that they would be flexible provided there was sufficient evidence of progress being made.

·       Concern over uncertainty around construction costs and the cost of the land on which the bridge would be built.

·       The bridge would alleviate traffic congestion in Ash and improve air quality

Following the debate in public, and upon the motion of the Deputy Mayor, Councillor Masuk Miah, seconded by Councillor Tom Hunt, the Council

 

RESOLVED: That under Section 100A (4) of the Local Government Act 1972 (as amended), the public be excluded from the meeting for consideration of Appendices 2, 3, 4, and 5 to the report and the Appendix to the Order Paper on the grounds that they involved the likely disclosure of exempt information, as defined in paragraphs 3 and 5 of Part 1 of Schedule 12A to the 1972 Act.

 

Following discussion in private of the contents of the exempt appendices referred to above, the Council resumed the meeting in public, and

 

RESOLVED: To approve the budget and funding strategy as set out in Exempt Appendices 2 and 3 to the report submitted to the Council,subject to the revisions to Appendix 3 as set out in the exempt Appendix 1 to the Order Paper circulated at the meeting.

 

Reasons:

This was a unique opportunity to utilise £23.9 million of central government funding towards the Ash Road Bridge Scheme to deliver an alternative road crossing of the North Downs railway line in close proximity to the Ash level crossing.  The Ash Road Bridge Scheme formed a requirement of Policy A31 of the Council's Local Plan which allocated land for housing in Ash. Delivery of this scheme would also enable the closure of Ash level crossing to motor vehicles, which would improve safety for highway and rail users and significantly reduce traffic congestion on the A323 and the use of alternative local roads to avoid the Ash level crossing in Ash.

 

Result of the Recorded Vote:

The motion to approve the budget and funding strategy above was approved, with thirty-four councillors voting in favour, one voting against, and four abstentions, as follows:

 

FOR:

AGAINST:

ABSTAIN:

Councillor Jon Askew

Councillor Christopher Barrass

Councillor Joss Bigmore

Councillor Chris Blow

Councillor Ruth Brothwell

Councillor Guida Esteves

Councillor Angela Goodwin

Councillor Angela Gunning

Councillor Gillian Harwood

Councillor Liz Hogger

Councillor Tom Hunt

Councillor Nigel Manning

Councillor Ted Mayne

Councillor Julia McShane

Councillor Ann McShee

Councillor Bob McShee

The Deputy Mayor,

Councillor Masuk Miah

Councillor Richard Morris

Councillor Marsha Moseley

Councillor George Potter

Councillor Jo Randall

Councillor John Redpath

Councillor Maddy Redpath

Councillor John Rigg

Councillor Will Salmon

Councillor Deborah Seabrook

Councillor Pauline Searle

Councillor Paul Spooner

Councillor James Steel

Councillor Cait Taylor

Councillor James Walsh

Councillor Fiona White

Councillor Keith Witham Councillor Catherine Young 

Councillor Graham Eyre

Councillor Paul Abbey

Councillor David Bilbé

Councillor Ramsey Nagaty

Councillor Susan Parker

 

 

Supporting documents: