Decision details

Guildford Park Development Agreement – Funding Condition Satisfaction

Decision Maker: Joint Strategic Director - Economy, Planning and Place

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Pursuant to clause 2.1 of the Development Agreement, the agreement is subject to the satisfaction of the following Conditions:
•the Funding Condition;
•the Building Contract Condition; and
•the Planning Condition,
which must all be satisfied before the Satisfaction Date is achieved.
The Council has received evidence from Wates Construction Limited in support of the Funding Condition.
The Funding Condition requires the Developer to demonstrate that:
•it has secured all funding necessary for the carrying out and completion of the Open Market Residential Units; and
•it continues to satisfy the Financial Standing Test to the degree achieved during the procurement process.
Having reviewed the information provided, the Council is satisfied that the Funding Condition has been fulfilled.
Accordingly, pursuant to the delegated authority granted under the Council's decision of 23 July 2024, approval is given to confirm that the Funding Condition set out in clause 2.1.1 and Schedule 2 of the Development Agreement has been satisfied.
For the avoidance of doubt, satisfaction of the Funding Condition alone does not constitute satisfaction of the Conditions under clause 2.1. The Development Agreement remains subject to the Building Contract Condition and the Planning Condition, both of which must also be satisfied before the Satisfaction Date can occur.

Reasons for the decision:

The Development Agreement requires the Council to determine whether the Funding Condition has been satisfied based on evidence provided by the Developer.
The Council is satisfied that:
•Wates Construction Limited has demonstrated that sufficient funding is available to complete the Open Market Residential Units
•the updated financial assessment confirms that Wates Construction Limited continues to satisfy the Financial Standing Test applied during the procurement process; and
•sufficient evidence has been provided to satisfy the requirements of the Funding Condition contained within Schedule 2 of the Development Agreement.
The decision is therefore limited to confirming satisfaction of the Funding Condition and does not constitute confirmation that the Building Contract Condition or Planning Condition have been satisfied. Those conditions will be considered separately in accordance with the provisions of the Development Agreement.

Alternative options considered:

The alternative option would be for the Council to conclude that the Funding Condition has not been satisfied.
This option was rejected because:
•Wates Construction Limited has provided written confirmation that it has secured funding for the development through its own resources.
•The Development Agreement expressly contemplates funding being provided through the Developer's own resources.
•An updated financial assessment has been completed using the financial standing criteria established during the procurement process.
•The assessment concludes that Wates Construction Limited continues to satisfy the required financial standing criteria and remains financially capable of delivering the development.
In light of the evidence provided, there is no reasonable basis for withholding confirmation that the Funding Condition has been satisfied. Approval of the Funding Condition is therefore considered to be in the best interests of the Council and the successful delivery of the Guildford Park Road housing scheme

Source of Authority to take Decision:

Council - 23 July 2024
CO29 GUILDFORD PARK ROAD REDEVELOPMENT: PARTNER SELECTION PREFERRED BIDDER
(5) To delegate to the Strategic Director (Place), in consultation with the Lead Councillor for Housing and Community and the Lead Councillor for Regeneration, all such approvals as are necessary to service the Council’s responsibility to provide approvals under the Development Agreement.

Publication date: 04/11/2026

Date of decision: 03/11/2026