Decision Maker: Joint Strategic Director - Place
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This decision is to approve the change of use
of a piece of land within the North Street Regeneration project
from bus station to land for landscaping and public realm. The Deed
is between the Council as freeholders and Carraway Ltd the long
leaseholder.
The decision will allow the developer, St
Edward, to undertake works as required by its contract with GBC and
the relevant planning consent. The decision will enable the Council
to seal the contract and complete this matter.
None.
The Executive on 26 October 2021 Item 4.
To authorise the Strategic Services Director, in consultation with
the lead Councillor for Regeneration and the Director of Resources,
to negotiate and enter into all associated property/contractual
documentation required in order to facilitate the sale of the
Council's interests in the Site, subject to receiving final
valuation advice from the Council's external advisors confirming
that the transaction amounts to the best consideration reasonably
obtainable.
Publication date: 04/04/2024
Date of decision: 04/04/2024