Decision Maker: Assistant Director: Regeneration and Planning Policy
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
In order to undertake works in the existing
public highway, it is necessary for a developer (Guildford Borough
Council in this case) to enter into an agreement with the Highway
Authority (Surrey County Council), to be given the permission to do
works.
This agreement will define the works to be done, which have been
technically approved by SCC, the cost of the works and any other
costs payable to SCC. These costs are outlined below.
To enter into a s278 Agreement for the
delivery of improvements to the existing public highway at Clay
Lane adjacent to the new SANG at Burpham Court Farm.
None
The Extraordinary Council on 30th August 2023, Item CO47:
The Council: Delegates to the Strategic Director of Place, in
consultation with the Lead Councillor for Regeneration and Lead
Councillor for Finance and Property, authority to enter into such
other contracts and legal agreements connected with the Weyside
Urban Village project as may be appropriate in compliance with
Procurement Procedure Rules and within the approved budget.
Publication date: 03/09/2024
Date of decision: 03/09/2024