Decision Maker: Assistant Director: Regeneration and Planning Policy
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
In order to undertake highway works in order
for this to be adopted, it is necessary for a developer (Guildford
Borough Council in this case) to enter into an agreement with the
Highway Authority (Surrey County Council), to agree the standard,
timescales and scope of highway to be improved, delivered and
adopted.
This agreement will define the works to be done, which have been
technically approved by SCC, the cost of the works and any other
costs payable to SCC. These costs are outlined below.
Costs payable to SCC:
12% fee = £181,200
Commuted sum = £481,000
Legal expenses = £2,000
Traffic Regulation Order = £15,000
Road Safety Audit = £2,000
Contingency = £34,060
Total payable to SCC = £715,260
SCC require that a cash bond or surety is provided as part of the
agreement which would cover the full cost of the works, with 10%
being released on the completion of the works and with this final
retention to be released on completion of the statutory maintenance
period (1 year).
GBC will be entering this agreement with their surety provider whom
they have already indemnified. The premium will be 0.9% on the cost
of works, for a minimum of two years and will be £27,180 for
this agreement.
To enter into a s38 Agreement for the delivery
and adoption of improvements to the existing Westfield Road and
connection to the Internal Estate Road
None
The Extraordinary Council on 30th August 2023,
Item CO47:
The Council: Delegates to the Strategic Director of Place, in
consultation with the Lead Councillor for Regeneration and Lead
Councillor for Finance and Property, authority to enter into such
other contracts and legal agreements connected with the Weyside
Urban Village project as may be appropriate in compliance with
Procurement Procedure Rules and within the approved
budget.
Publication date: 27/08/2024
Date of decision: 19/07/2024